BGN Building Expansion
The Local Authority have asked BGN to take in an extra two forms of entry. This will require a new teaching block, hall and other internal upgrades.
Update on progress
The new buildings are taking shape and are now truly “ Out of the ground” with the steel up for the new hall and brick work started.
The main teaching block is slight behind the hall as it is a 2-story building, but all steel is now on site and completion of the steel erection is expected before half-term.
The main work on the Maths and English roof is complete and with work schedules over half-term for the kitchen roof the project is on target to be completed in March